Projects

  UNDERPASS OF KARTAL BRIDGE AND CONNECTION ROADS CONSTRUCTION
  Construction of underpass junction which is connecting the lateral roads of E5 under the connection road connecting E5 road to TEM highway. Bridge construction with prestressed beam system with span length of 26 meter applied as construction method. Foundation system is Ø120 mm piled, side coverings have been executed by precast side panels. In scope of the work, displacement of 750 meter water pipeline with diameter of Ø2200 has also been executed. Construction of storm water and sewerage lines with various diameters has been executed. Pedestrian underpass, vehicle underpass, kerb and sidewalk construction and landscaping work of green areas have also been executed in scope of the work.